Dominion Energy gas plant approval suspended after Virginia regulators reverse decision on controversial $1.47 billion Chesterfield project

Created on:

By: Patrick Graham

Dominion Energy’s controversial $1.47 billion Chesterfield gas plant received a major setback as Virginia regulators abruptly paused approval this week. The State Corporation Commission suspended its November 25 final order, reopening reconsideration of the 944-megawatt facility amid mounting environmental and health concerns. This dramatic reversal throws the utility’s energy expansion plans into uncertainty.

🔥 Quick Facts

  • Chesterfield Energy Reliability Center (CERC) was initially approved on November 25, 2025 by Virginia regulators
  • On December 18, 2025, the SCC granted reconsideration and suspended the approval following a formal appeal
  • The project would add 2.2 million tons of CO2-equivalent emissions to Dominion’s annual carbon footprint
  • Environmental groups argue SCC failed to comply with Virginia’s Clean Economy Act and Environmental Justice Act requirements

The Sudden Pause That Changes Everything

Virginia’s State Corporation Commission made a stunning reversal on Tuesday when it granted reconsideration of the Chesterfield gas project. The SCC had approved the plant just three weeks earlier on November 25, but now suspended that final order entirely while it considers a formal appeal petition.

The reconsideration request came from Appalachian Voices, the Chesterfield NAACP, and Mothers Out Front, represented by the Southern Environmental Law Center. These groups immediately challenged the commission’s approval, arguing regulators disregarded critical state laws requiring analysis of environmental and health impacts on disadvantaged communities.

The suspension means no timeline exists for a final decision, leaving Dominion Energy in regulatory limbo. The utility can no longer move forward with its controversial project while the commission reconsiders the petition.

What Environmental Groups Say Went Wrong

The appeal petition raises three major legal challenges to the SCC’s November approval. First, the groups contend the commission failed to adequately analyze emissions impacts on fenceline communities—defined under state law as low-income or communities of color near major pollution sources.

Second, the petition challenges whether Dominion demonstrated that the plant is actually necessary for grid reliability. Opponents argue the utility provided only “minimal evidence” to justify the infrastructure despite claiming it meets reliability needs by 2029. Third, they contest whether the utility met state energy efficiency requirements, which should be prerequisite to building new fossil fuel capacity.

Grayson Holmes, a senior attorney with the Southern Environmental Law Center, stated the commission’s willingness to reconsider was encouraging. The organization emphasized that permitting this exception on weak evidence “sets a bad precedent” for future gas proposals in Virginia.

The Project’s Scale and Controversy

Project Details Information
Facility Name Chesterfield Energy Reliability Center (CERC)
Capacity 944 Megawatts (4 combustion turbines)
Investment Cost $1.47 Billion
Annual Emissions 2.2 Million Tons CO2-Equivalent
Proposed Online Date 2029
Cost Recovery Rider $35.7 million from customers in 2026 rate year

The 944-megawatt natural gas plant would be built on the site of a former coal power station in Chesterfield County that operated from 1952 until 2023. Originally approved by the SCC on November 25, the project would cost ratepayers roughly $35.7 million annually during the 2026 rate year through a rider charge.

The plant was designed to operate as a “peaker plant,” providing rapid capacity during peak demand periods. Dominion claims it can dispatch electricity within 10-15 minutes, making it crucial for grid stability during extreme demand scenarios.

The Clean Economy Act Conflict at the Heart of the Debate

The dispute centers on a fundamental tension in Virginia’s energy policy. The Clean Economy Act (VCEA), passed in 2020, explicitly encourages utilities to transition to renewable energy and phase out all fossil fuel plants by 2045. Yet it includes a narrow exception allowing new gas plants if utilities can prove grid reliability needs justify them despite renewable alternatives being unavailable.

Dominion invoked this reliability exception, arguing that data center demand growth creates an urgent need for dispatchable natural gas capacity. The commission agreed with this reasoning in its November decision, specifically citing evidence from PJM Interconnection (the regional grid operator) and other studies supporting a reliability threat.

However, critics say the utility’s “all of the above” energy strategy essentially abandons Virginia’s clean energy commitments. Walton Shepherd, Virginia director at the Natural Resources Defense Council, said the SCC “could have held Dominion’s feet to the fire” but instead “took Virginia back in time.” Environmental groups argue Dominion failed to adequately pursue battery storage and true renewable alternatives.

Will Regulators Change Course or Reaffirm the Decision?

The commission’s acceptance of the reconsideration request does not guarantee it will reverse its November approval. The SCC’s decision to grant reconsideration was a procedural ruling that obligates regulators to examine the petition’s arguments more thoroughly while suspending the original order.

Dominion spokesperson Jeremy Slayton defended the project, stating it was “approved after a year of exhaustive review, an extensive public hearing and participation by thousands of Virginians.” The company maintains that CERC is essential for grid reliability and represents “good news for our customers, Virginia’s economy and the reliability of the grid.”

Community members and environmental advocates have signaled they are prepared for a prolonged fight. Nicole Martin, local NAACP president in Chesterfield, said the coalition opposing the project will continue pressing regulators to reject it entirely. Environmental lawyers argue that approving the plant despite Dominion’s failure to meet energy efficiency targets violates state law.

What happens next with the Chesterfield gas plant?

The SCC has not set a timeline for issuing a final decision on the reconsideration petition. The suspension means regulators must thoroughly examine legal arguments about compliance with the Clean Economy Act and Environmental Justice Act before proceeding. During this period, Dominion cannot move forward with construction permits or financing arrangements, effectively freezing the project indefinitely.

Sources

  • The Center Square – Comprehensive reporting on the SCC’s suspension order and petition arguments
  • VPM News – Detailed analysis of environmental justice law implications and appeal process
  • Inside Climate News – In-depth examination of data center demand and regulatory context

Red94 is an independent media. Support us by adding us to your Google News favorites:

Leave a review